Daily Fault Report Date: 10 APRIL 2018
No. |
Client Centre |
Feeder |
Nature of Fault |
Date of Fault |
Number of Affected Customers |
Expected Date of Restoration |
Responsibility |
1.0 | REDCLIFF | 11kV Chiwundura Feeder | Line Fault |
09/04/2018 |
200 |
10/04/2018 |
District Manager(Kwekwe) |
2.0 |
REDCLIFF | 11kV Zhombe Feeder | Line Fault |
10/04/2018 |
500 |
10/04/2018 |
District Manager(Kwekwe) |
3.0 |
ZVISHAVANE | 11kV Rural Feeder | Poles Down |
08/04/2018 |
100 |
11/04/2018 |
Principal Engineer (Zvishavane) |
Comments: 1.0 The Chiwundura Feeder faulted on 09/04/2018 and the fault was still being located. The expected power restoration date is 10/04/2018.
2.0 The Zhombe Feeder faulted on 10/04/2018 and the fault was being located. The expected power restoration date is 10/04/2018 3.0 The Zvishavane Rural Line fault was located as 9 poles down. The feeder faulted on 08/04/2018 and the expected power restoration date is 11/04/2018. Work In Progress.
|
Eng. G. Kasipo
Engineering Manager – Southern