ZIMBABWE ELECTRICITY TRANSMISSION & DISTRIBUTION COMPANY
SOUTHERN REGION
Daily Fault Report Date: 16 April 2018
Client Centre |
Feeder |
Nature of Fault |
Date of Fault |
Number of Affected Customers |
Expected Date of Restoration |
Responsibility |
|
1.0 | ZVISHAVANE | 11kV Buchwa-Zvomukonde T-Off | Poles Down |
13/04/2018 |
150 |
16/04/2018 |
Principal Engineer (Zvishavane) |
2.0 | NEMBUDZIYA | 33kV Siakobvu Feeder | Poles Down |
10/04/2018 |
350 |
17/04/2018 |
District Manager
(Kwekwe) |
3.0 | NKAYI | 11kV Dakamela Feeder | Line Fault |
14/04/2018 |
10 |
16/04/2018 |
District Manager
Kwekwe) |
Comments:
1.0 The Buchwa-Zvomukonde T-Off Line faulted on 13/04/2018 and was partially restored. The fault was located as 3 poles down and the expected power restoration date is 16/04/2018 2.0 The Siakobvu Line faulted on 10/04/2018 and the faulted was located as poles down. The expected power restoration date is 17/04/2018 3.0 The Dakamela T-off Feeder faulted on 14/04/2018 and the fault was being located. The expected power restoration date is 16/04/2018
|
Eng. G Kasipo
Engineering Manager – Southern