ZIMBABWE ELECTRICITY TRANSMISSION AND DISTRIBUTION COMPANY (ZETDC) PVT LTD
DAILY FAULT REPORT
Northern Region
Wednesday 11 April 2018
- 1. Moven 11kv (Chegutu)
Nature of Fault: No power
Fault occurred on – 10.04.18 @ 1630hrs
Number of customers affected – 50
Outage Duration:
Estimated Restoration Time – 1640hrs
- 2. North east 11kv (Kadoma)
Nature of Fault: No power
Fault occurred on – 10.04.18 @ 0718hrs
Number of customers affected –200
Outage Duration:
Estimated Restoration Time – 2215hrs
- 3. Katawa 11kv (Chegutu)
Nature of Fault: No power
Fault occurred on – 10.04.18 @ 0632hrs
Number of customers affected –350
Outage Duration:
Estimated Restoration Time – 1820hrs