ZIMBABWE ELECTRICITY TRANSMISSION & DISTRIBUTION COMPANY
WESTERN REGION
Daily Fault Report (11kv, 33kv)
Date: 19 April 2018
HWANGE
01. Client Centre Hwange
Feeder Mcetshwa 11kv
Areas Affected: Mcetshwa, Mathuphula and Tshino
Nature of Fault: 2 poles down
Date of Fault: 24 December 2017 @ 1500hrs
Number of affected customer: 6
Expected restoration: Awaiting Contractor
02. Client Centre: Hwange
Feeder St Paul’s
Areas Affected: Lake Alice, St Paul and Lupaka
Nature of Fault: Poles down
Date of Fault: 23 December 2017 @ 0600hrs
Number of affected customer: 12 Expected restoration: Awaiting Contractor
03. Client Centre Hwange
Feeder Mzola 33kv
Areas Affected: Dandanda
Nature of Fault: Poles down
Date of Fault: 01 January 2018 @ 1500hrs
Number of affected customer: 06
Expected restoration: Awaiting Contractor
04. Client Centre Hwange
Feeder Insuza 11kv
Areas Affected: Mathabisana
Nature of Fault: Unknown
Date of Fault: 15 February 2018
Number of affected customer: 12
Expected restoration: 20 April 2018
05. Client Centre Hwange
Feeder Hwange Local 33kv
Areas Affected: Makwandara
Nature of Fault: Pole down Date of Fault: 07 March 2018
Number of affected customer: 01
Expected restoration: 20 April 2018
06. Client Centre Hwange
Feeder Hwange Local 33kv
Areas Affected: Namatela T-off
Nature of Fault: Pole down Date of Fault: 18 April 2018
Number of affected customer: 01
Expected restoration: 19 April 2018
07. Client Centre Hwange
Feeder Gwayi 33kv
Areas Affected: Skumi T-off
Nature of Fault: Pole down Date of Fault: 18 April 2018
Number of affected customer: 01
Expected restoration: 19 April 2018
GWANDA
01. Client Centre Gwanda
Feeder Dambashoko T/Off
Areas Affected: Dambashoko School and Mkazhe School
Nature of Fault: Disc insulators broken
Date of Fault: 23 February 2018
Number of affected customer: 20
Expected restoration: 20 April 2018
02. Client Centre Gwanda
Feeder Maphisa 11kv
Areas Affected: Arda/ Track, Homestead Business Centre, Fanyet Sun Business Centre, Chelanyemba Hospital and Chelanyemba Centre
Nature of Fault: Copper Conductors stolen
Date of Fault: 25 February 2018
Number of affected customer: 100
Expected restoration: 20 April 2018
03. Client Centre Gwanda
Feeder Big Ben 11kv
Areas Affected: Timber Farm T/Off
Nature of Fault: Copper Conductors stolen
Date of Fault: 16 April 2018
Number of affected customer: 08
Expected restoration: 20 April 2018
BEITBRIDGE
01.Client Centre Beitbridge
Feeder Bubi 11kv
Areas Affected: Chief Matibhe
Nature of Fault: 5 Poles down
Date of Fault: 31 December 2017 @ 1900hrs
Number of affected customer: 4
Expected restoration: 20 April 2018
02.Client Centre Beitbridge
Feeder Mazunga/Shashe 33kv
Areas Affected: Mpande Business Centre
Nature of Fault: 4 Poles down
Date of Fault: 04 February 2018
Number of affected customer: 8
Expected restoration: 20 April 2018
ESIGODINI – NIL
BULAWAYO ENVIRONS DEPOT – NIL
PLUMTREE – NIL